How to use pointer routings in Manufacturing in Microsoft Dynamics GP


INTRODUCTION

This article discusses how to use pointer routings in Manufacturing in Microsoft Dynamics GP.

↑ Back to the top


More Information

The purpose and the use of pointer routings

Pointer routings are an ideal tool if you have a series of routing sequences that are common to multiple finished-good items. To use pointer routings, you must use operation codes. An operation code defines the information that is common to a single routing sequence.

For example, in a bakery, the following are the common tasks that will become routing sequences:
  • Bake
  • Cool
  • Package
The length of time for each task in the routing sequence may vary slightly. But you use similar labor codes and machine IDs regardless of the item that you produce.



You must define an operation code for each task. For example, the operation code for the Bake task includes an applicable description, a work center, and the machine ID information for the oven or the ovens that will be used. You can also supply estimates for the machine time and for the cycle time. When you supply these estimates, you do not have to enter data for the machine time and for the cycle time. Instead, you only have to edit the data.

After you define an operation code for each task, you create a pointer routing that groups the operation codes for the three tasks. You create the pointer routing so that you are prompted to add all three tasks as three routing sequences when you add the first task to an item’s routing sequence.

Pointer routing preferences

If you want to use pointer routings, you must enable pointer routings in the Routing Preference Defaults window. To do this, follow these steps:
  1. On the Tools menu, point to Setup, point to Manufacturing, point to System Defaults, and then click Routings.
  2. In the Routing Preference Defaults window, click to select the Use Pointer Routings check box.
  3. Click OK.

Operation codes

To create operation codes, follow these steps:
  1. On the Cards menu, point to Manufacturing, point to Routings, and then click Operations. The Operations Setup window opens.
  2. In the Work Center ID list, select the work center in which the sequence will occur.
  3. In the Operation Code box, type an operation code. The Operation Code box represents an alphanumeric field that is used to uniquely identify this operation.
  4. Type any additional information in the following fields:
    • Setup Time
    • Setup Labor Code
    • Labor Time
    • Run Labor Code
    • Machine Time
    • Machine ID
    • Queue Time
    • Move Time
    • Cycle Time
    Enter as much information as you can so that you will save time later when you create the individual routings.
  5. Click Insert to insert the operation code into the list at the bottom of the window. This action enables the operation code for the work center that you selected.

Define the pointer routings

To define pointer routings, create the header record and then add any sequences that you want. To do this, follow these steps:
  1. Create the header record. To do this, follow these steps:
    1. On the Cards menu, point to Manufacturing, point to Routings, and then click Ptr Rtg Creation.
    2. In the Pointer Routing Creation window, type a pointer routing name in the Pointer Rtg. Name box.
    3. In the Work Center ID list, select a work center for the first task in the routing sequence.
    4. In the WC Opcode list, select an operation code for the first task in the routing sequence.
    5. Click Save.
  2. Add the sequences. To do this, follow these steps:
    1. On the Transactions menu, point to Manufacturing, point to Routings, and then click Pointer Edit. The Pointer Routing Edit window opens.
    2. In the Pointer Rtg. Name list, select the pointer routing that you created in step 1.
    3. In the Work Center ID list, select a work center for the second task in the routing sequence.
    4. In the WC Opcode list, select an operation code for the second task in the routing sequence.
    5. Click Insert.
    6. Repeat steps 3 through 5 for any additional tasks.

Use the pointer routings to create new finished-good routings

  1. On the Cards menu, point to Manufacturing, point to Routings, and then click Routings Entry.
  2. In the Routing Sequence Entry window, enter a new routing sequence for the first task in the routing sequence. To do this, accept the default value in the Sequence Number field. Or, type a new value in the Sequence Number field. In the Work Center ID list, click a work center for the first task.
  3. In the Work Center Opcode list, click the operation code for the first task in the routing sequence.

    Note Make sure that you click the same work center and the same operation code that you clicked when you created the pointer routing header record.
  4. The Pointer Routing window opens behind the Routing Sequence Entry window. Move the Routing Sequence Entry window. Or, click Windows, and then click Pointer Routing.
  5. In the Pointer Routing window, select the pointer routing that you want to use in the Pointer Rtg Name list. If you have to, change the information in the Sequence Number box and in the Increment Sequence by box to control the numbering of the sequences that will be added.
  6. Click OK.
  7. In the Routing Sequence Entry window, review the sequences that you added to the routing, and then make any adjustments that are required.

↑ Back to the top


Keywords: kbexpertiseinter, kbexpertisebeginner, kbmbspartner, kbinfo, kbmbsmigrate, kb

↑ Back to the top

Article Info
Article ID : 930347
Revision : 1
Created on : 1/7/2017
Published on : 7/14/2012
Exists online : False
Views : 78