This update fixes the following issues:
You cannot assign a cost value to a cost resource through the Assign Resource dialog box if the Windows regional setting is set to Norwegian. Instead, you see the following error message:
This field only supports numbers.
If you’ve only typed numbers, try entering a smaller number with up to two decimal places.
Consider the following scenario:
- You are using the German version of Project 2016.
- You set the date format to use Weeks. For example, “3/W05".
- You create an automatically scheduled task.
- You modify either the Start or Finish field to change the date.
In this scenario, you receive the following error message:
The date you entered isn't supported for this field. Dates must be between January 1, 1984, through December 31, 2149.
Enter the date in the correct format, eg., 15/06/00 or 15 June 2000
Consider the following scenario:
- You have a Project Web App site and Project Professional 2016 in your organization.
- You create some custom project fields and add them to your project detail pages (PDPs).
- In Project Web App, you create a new project and add values to these custom fields.
- You open the project in Project Professional 2016, make a change and then save the project.
- You open the project in Project Web App and view the custom field values on the PDPs.
In this situation, the values for these custom fields may be lost.
Consider the following scenario:
- You have a task that has a resource assigned.
- The task has a split in it. For example, there's a week of work, a week where no work exists and then a final week that has work.
- In the timesheet for this task, you enter hours on the task so that the work is completed up to the date where the split begins.
- The timesheet is submitted and then the status update is approved.
- After that, the project is opened in Project Web App and the task finish date is adjusted to a date that's after where the actual work is completed. For example, the actual finish date is set to the middle of the week where there's no work.
In this situation, the actual work is spread over the whole duration.