To work around this behavior, display the hidden (collapsed) subtasks or assignments.
To display hidden subtasks in a task view such as the Gantt Chart in Project 2010, follow these steps:
- On the View tab, click Gantt Chart.
- Click the heading of the Task Name column to select all tasks.
- On the View tab, click Outline, and then click All Subtasks.
To display hidden subtasks in a task view such as the Gantt Chart in Project 2007 and earlier versions, follow these steps:
- On the View menu, click Gantt Chart.
- Click the heading of the Task Name column to select all tasks.
- On the Project menu, point to Outline, point to Show, and then click All Subtasks.
To display hidden tasks' assignments in a Resource Usage view, or resourve assignments in a Task Usage view in Project 2010, follow these steps:
- On the View tab, click Resource Usage or Task Usage.
- Click the heading of the Resource Name column or Task Name column to select all rows and assignments.
- On the Project menu, click Outline, and then click All Subtasks.
To display hidden tasks' assignments in a Resource Usage view, or resource assignments in a Task Usage view in Project 2007 and earlier versions, follow these steps:
- On the View menu, click Resource Usage or Task Usage.
- Click the heading of the Resource Name column or Task Name column to select all rows and assignments.
- On the Project menu, point to Outline, and then click Show Assignments.